Palomar Medical Center West: A Look Ahead
Palomar Medical Center West – Proposed Campus
(450 beds):
Hospital - 750,000 sq. ft.
- 168 Acuity Adaptable beds
- 192 Med/Surg beds
- 12 Operating Rooms
- 6 Cath. Labs. / Interventional
- Radiology Rooms
- 48 E.D. Exam/Tx + 2 Trauma Rooms
- 17 Imaging Rooms
Three month look ahead
- Activities through 2007
- Rock crushing, blasting of rock
- Selection of concrete contractor
- Detailing for foundations (reinforcing steel, rock anchors and anchor bolts)
- Steel mill order
- Complete hospital basement excavation
- MEP systems fully coordinated in BIM model (Basement through Level 3)
Entire project look ahead
- Major Milestones
- Steel erection July 2008
- MEP overhead rough-in December 2008
- Drywall (non-priority) begins April 2009
- Steel topping off July 2009
- Tower roof complete March 2010
- Tower weather-tight March 2010
- Building energized March 2010
Elevators ready to use April 2010
- Central plant ready to occupy Fall 2010
- Hospital ready to occupy early 2012
Womens & Childrens Hospital –150,000 sq. ft.
(date of project and build to be determined)
- 20 LDR / Ante-Partum Rooms
- 44 Post-Partum Beds
- 16 Pediatric Beds
- 16 NICU Beds